TechWhirl (TECHWR-L) is a resource for technical writing and technical communications professionals of all experience levels and in all industries to share their experiences and acquire information.
For two decades, technical communicators have turned to TechWhirl to ask and answer questions about the always-changing world of technical communications, such as tools, skills, career paths, methodologies, and emerging industries. The TechWhirl Archives and magazine, created for, by and about technical writers, offer a wealth of knowledge to everyone with an interest in any aspect of technical communications.
Subject:Rules of thumb in estimating From:Matthew J Long <mjl100z -at- MAIL -dot- ODU -dot- EDU> Date:Tue, 8 Jul 1997 08:44:17 -0400
On Mon, 7 Jul 1997, Cramer, Kim wrote:
> This is how it works here:
>
> 1. We estimate time to completion for each book for each release, then
> we track actual time. We're expected to estimate within +/- 10% of
> actual. This comparison helps us become better at estimating for future
> projects so they are more likely to stay on track for the estimated
> release date.
>
Kim,
I landed a great job as a technical writer only 6 months out of college in
which I am the only (and therefore Lead) tech writer. I call all the shots
as far as design, usage, conventions, etc. I learned a lot in my
internship and with the work I have done so far (I have now been doing
this for 9 months) and my company likes my work and seems confident in my
skills. However, I start to get concerned about the amount of time it
should take to produce a user's manual. In my internship, things were very
laid back--no deadlines. Well, the real world just ain't like that. I
haven't had any major deadlines so far, but I think that is just because
my bosses have no idea how long a user's manual should take.
When I read your comment (above), I thought it would be a good idea to ask
you, but also anyone else, how to estimate the amount of time it should
take to produce a manual. I am aware that the answer is going to depend
on the application and how many "features" is sports. But I would love to
know how you get started. When I used to paint houses during my summers
in college, the only way I could be accurate in my estimates to the
customer was through trial and error, Sometimes I would underestimate and
lose my butt, while other times it was the opposite. I would bet that the
same is true in estimating the time it takes to complete a manual, but I
would also bet that there are a few rules of thumb. Can you advise?
I welcome any comments!!
Thanks!
////////////////////////////**************************************
Matthew J. Long
Technical Writer
mjl100z -at- mail -dot- odu -dot- edu
matt -dot- long -at- justice -dot- usdoj -dot- gov
-When you can't be eloquent, choose brevity!
********************************************************////////////
TECHWR-L (Technical Communication) List Information: To send a message
to 2500+ readers, e-mail to TECHWR-L -at- LISTSERV -dot- OKSTATE -dot- EDU -dot- Send commands
to LISTSERV -at- LISTSERV -dot- OKSTATE -dot- EDU (e.g. HELP or SIGNOFF TECHWR-L).
Search the archives at http://www.documentation.com/ or search and
browse the archives at http://listserv.okstate.edu/archives/techwr-l.html